FERC Filings
COMPLAINT REQUEESTING FAST TRACK PROCEDURES, PJM INTERCONNECTION, L.L.C.
SERVICE
The Complainants have served a copy of this Complaint by internet transmission and overnight delivery on the following counsel for PJM:
Richard A. Drom, Esq.
PJM Interconnection, LLC
Valley Forge Corporate Center
955 Jefferson Avenue
Norristown, Pennsylvania 19403-2497
Barry S. Spector, Esq.
Wright & Talisman, PC
1200 G St, N.W., Suite 600
Washington, D.C. 20005-3802
WHEREFORE, for the foregoing reasons, the Commission should issue an Order finding that the procedure followed by PJM in its attempt to eliminate certain payments for Operating Reserves renders such action invalid and ineffective, and that the Commission should utilize Fast Track procedures to resolve this matter.
Respectfully submitted,
Atlantic City Electric Company by Tsion M. Messick
Camden Cogen, L.P. by Ross Ain
Delmarva Power & Light Company by Tsion M. Messick
Edison Mission Marketing & Trading, Inc. by Sam C. Henry
Electric Power Supply Association by Julie Simon
FPL Energy, Inc. by Mary Margaret Farren
New Energy Inc. by Gustav Beerel
Old Dominion Electric Cooperative by John Rainey
PECO Energy Company by Ellen Cavanaugh
PG&E Energy Trading-Power, L.P. by Sarah M. Barpoulis
PG&E Generating Company by Sanford L. Hartman ,br>
Sithe Power Marketing, L.P. by Scott A. Weiner
Strategic Energy L.L.C. by James P. McCormick
Virginia Electric and Power Company by Michael Regulinski
Williams Energy Marketing and Trading Company by Michael S. Grim
WPS Energy Services, Inc. by Mark A. Radtke
Stephen A. Herman, Esq.
Michael J. Gergen, Esq.
Ona Alston Dosunmu, Esq.
LATHAM & WATKINS
1001 Pennsylvania Avenue, N.W., Suite 1300
Washington, D.C. 20004
Counsel for Sithe Power Marketing, L.P.
January 21, 2000