FERC Filings
PROTEST OF THE ELECTRIC POWER SUPPLY ASSOCIATION re: PJM INTERCONNECTION, L.L.C.
REQUEST FOR RELIEF
For the foregoing reasons, EPSA requests that the Commission grant the following relief: (1) grant rehearing of the May 15th Order; and (2) issue a stay of the portion of the May 15th Order accepting the revisions to the MMP pending rehearing and discussions of issues in a stakeholder process, including the revisions to PJM West included in the June 19th Supplemental Filing.
Dated: July 10, 2002
Respectfully submitted,
___________________________
Julie Simon, Vice President of Policy
Nancy Bagot, Sr. Manager of Policy
Electric Power Supply Association
1401 New York Avenue, 11th Floor
Washington, DC 20005
(202) 628-8200
CERTIFICATE OF SERVICE
I hereby certify that I have served a copy of the comments by first class mail, postage prepaid, upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., July 10, 2002.
______________________
Julie Simon