FERC Filings
Motion for Leave to Intervene and Comment of EPSA re: ISO New England Inc., Bangor Hydro-Electric Co., NSTAR Electric & Gas Corp., New England Power Co., Northeast Utilities Service Co., The United Illuminating Co. and Vermont Electric Power Co.
Conclusion
WHEREFORE, based on the discussion above, EPSA requests that the Commission provide necessary guidance on aspects of the proposal as filed and defer final consideration of the proposal for 90 days to grant parties additional time to determine whether they can resolve differences based on such guidance and present a voluntary, mutually agreeable Order No. 2000 proposal for New England. EPSA urges the Commission to require that the ISO-NE establish an RTO market structure that improves upon the current ISO market, without compromising the independence of the system operator.
December 8, 2003
Respectfully submitted,
Julie Simon, Vice President of Policy
Nancy Bagot, Senior Manager of Policy
Electric Power Supply Association
1401 New York Avenue, NW
11th Floor
Washington, DC 20005
(202) 628-8200
CERTIFICATE OF SERVICE
I hereby certify that I have served a copy of the comments by first class mail, postage prepaid, upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., December 8, 2003.
________________________
Julie Simon