• CONTACT US
  • SITE MAP
Advocating the power of competition

FERC Filings

Motion of EPSA for Leave to Intervene and Comment re: Devon Power LLC

Preface

Devon Power, LLC, et al.
Docket No. ER03-563-030

Pursuant to Sections 211 and 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (FERC or Commission), 18 C.F.R. § 385.211 and 385.214, the Electric Power Supply Association (EPSA) respectfully files this motion for leave to intervene out of time and comment in the above-captioned proceeding. On March 1, 2004, ISO New England Inc. (ISO-NE) submitted a compliance filing (March 1 filing) reflecting a comprehensive locational capacity proposal (Locational ICAP) for New England pursuant to the Commission’s Order issued April 25, 2003, 103 FERC 61,082 (April 25 order). EPSA supports the implementation of a locational ICAP mechanism in New England. However, there are details in the March 1 filing that should be revised.